Uncertainty over the new Greece-Italy cable: Italian energy regulator calls for a review of timeline and costs

Arera calls for priority to be given to the northern border, while expressing strong reservations about the extension to the southern lines with Greece and Tunisia

Newsroom August 12 03:22

As Athens and Rome push for the creation of a new electrical “corridor” between Greece and Italy, Italy’s energy regulator Arera is sending a clear message that the immediate priority is the country’s northern interconnections.

In a recent submission to the operator of the Italian transmission system Terna, Arera called for priority to be given to the projects deemed most cost-effective, namely the expansion of interconnection capacity to the north by at least 2.6 GW. For the southern lines – with Greece and Tunisia – the authority expresses significant reservations, especially regarding the time horizon of the benefits for Italy.

>Related articles

PPC: Stable prices in household tariffs in January despite the rise in wholesale prices

China: Surreal images show entire mountains covered with solar panels (video)

Ministry of Environment and Energy: Green light for exploration in the “South Peloponnese” offshore area

Positions on the timetable

The new Greece-Italy interconnection, with a capacity of 1,000 MW, is planned to be completed between 2033 and 2035. However, according to Arera, “substantial benefits” for Italy are expected only after 2040, leading the authority to recommend a review of the timetable.

The issue of costing is also on the table, as Arera is asking for additional analysis. In the documents submitted by Terna for the selection process of this year’s PCI/PMI projects, the estimate reaches 1.9 billion euros, while in the 10-year programs of ADMIE and ENTSO-E the corresponding amount is 1.25 billion euros.

The figure of 1.1 billion euros is 1.1 billion euros.

Ask me anything

Explore related questions

#energy#Greece-Italy cable
> More Economy

Follow en.protothema.gr on Google News and be the first to know all the news

See all the latest News from Greece and the World, the moment they happen, at en.protothema.gr

> Latest Stories

FBI searches the home of a Washington Post journalist who covered the Trump administration’s firing of federal employees

January 14, 2026

RealPolls: New Democracy above its European election result, Plefsi returns to second place – With a change of leader ND loses nearly two points, PASOK gains 5.5

January 14, 2026

Countdown to a U.S. strike on Iran: Americans and Britons evacuate bases, direct assassination threat against Trump from Tehran – Live

January 14, 2026

Direct assassination threat against Trump from Iran: “This time the bullet will not miss the target”

January 14, 2026

32 dead after a crane falls on a passenger train in Thailand

January 14, 2026

Meeting between Mitsotakis and the “agro-leaders” of the blockades set for Friday

January 14, 2026

Pierrakakis: We will achieve even more through collective effort

January 14, 2026

“All cash”: Netflix is preparing a strategic move to accelerate its $83 billion deal with Warner Bros.

January 14, 2026
All News

> Politics

RealPolls: New Democracy above its European election result, Plefsi returns to second place – With a change of leader ND loses nearly two points, PASOK gains 5.5

The appeal of Tsipras and Karystianou as reflected in the Real Polls survey for Protagon – What is recorded in voting intention and projected election results – SYRIZA sinks

January 14, 2026

Pierrakakis: We will achieve even more through collective effort

January 14, 2026

Plakias on Karystianou: There isn’t just one “mother of Tempi,” there are many – No relatives will follow her into her party

January 14, 2026

Tsiaras on farmers: The State cannot operate with obsessions, egos, and stubbornness — We are waiting their response

January 14, 2026

Mitsotakis at a law firm for the presentation of the new digital court file

January 14, 2026
Homepage
PERSONAL DATA PROTECTION POLICY COOKIES POLICY TERM OF USE
Powered by Cloudevo
Copyright © 2026 Πρώτο Θέμα